Skip to main content

Equipment Verification

GatherLive Server Cluster

Verify the following equipment is available and operational:

Equipment

Quantity

Notes

Lenovo P16 Gen 2 laptops (or current standard server nodes)

3

Pre-configured prior to deployment

Ubiquiti 10GbE USB-C Ethernet Adapters

3

Required for server networking

UniFi 5-Port Managed Switch

1

Dedicated server cluster switch

Network Infrastructure

Equipment

Purpose

UniFi Dream Machine Pro (UDM Pro)

Network gateway and DHCP services

UniFi 24-Port Managed Switch (or equivalent)

Primary event switch

RJ45 SFP+ Transceiver

10GbE uplink between switches

Additional Managed Switches

As required by venue layout

Upload Stations

  • Use matching Lenovo laptops whenever possible.
  • If Mac file support is required, provide an appropriate number of MacBook Pro systems.
  • Plan approximately one upload station for every 20 presentations during peak operating periods.
  • Increase station counts for events with longer presentations or concentrated upload windows.

Presentation Laptops

Operated Rooms

  • Two Windows laptops for presentation switching.
  • One additional backup Windows laptop when required.
  • One Mac laptop if Mac presentation support is needed.

Self-Service Rooms

  • One Windows presentation laptop on the lectern.
  • Add a Mac laptop when required by event specifications.

Venue Requirements

Presentation Distribution Network

Provide a dedicated "Dry VLAN" with:

  • No internet access.
  • No additional network services.
  • One network drop in the Speaker Ready Room.
  • One network drop in each presentation room.

Internet Connection

Provide:

  • One hard-wired internet connection in the Speaker Ready Room.
  • No captive portal or splash page.
  • Standard DHCP addressing.
  • Private IP addressing preferred.

Optional Connectivity

If venue internet is unavailable:

  • Use the approved Pepwave 5G router as the WAN connection for the UDM Pro.